03Tool · UPS runtime calculator
How long will your UPS keep things running when the power cuts?
Load, UPS rating and batteries in: load check and estimated runtime.
Runs in your browser. Nothing is sent unless you choose to.
This calculator needs JavaScript. Our engineers can measure your real load and runtime on site.
Long power cuts? Batteries charged by solar keep the rack running longer. Solar power
More about this tool
Related guideHow to size a UPS for your network rack
Measure the load, pick the rating with headroom, then choose batteries for the runtime you actually need.
Read the guide01How it is calculated
- 01
Load check: load W ÷ UPS W. Up to about 80% leaves room to grow.
- 02
Battery current per string = W ÷ (0.9 × V per string) ÷ strings. The 0.9 allows for losses in the UPS inverter.
- 03
Runtime uses Peukert's law, which describes how lead-acid batteries give less capacity at higher current: hours = 20 × (Ah ÷ (I × 20))^1.15. The 20 is the usual 20-hour Ah rating; 1.15 is a typical exponent for sealed lead-acid batteries.
- 04
The result is then reduced by the age factor: 0% for new, 20% for 1–3 years, 40% for older batteries or hot rooms.
Worked example
1,200 W on a UPS with 8 × 12 V 9 Ah batteries (96 V), one string, new. Current = 1,200 ÷ (0.9 × 96) ≈ 13.9 A. Runtime ≈ 20 × (9 ÷ 278)^1.15 ≈ 0.39 h, about 23 minutes. A simple energy calculation would say about 39 minutes.
02Treat this as an estimate
- Manufacturers publish runtime charts for each model and battery pack. Where you have one, it beats any formula.
- The estimate is less reliable at very high or very low loads, and with mixed or mismatched batteries.
- Batteries are usually replaced when capacity falls to about 80% of new. In a hot server room that can come within two or three years.
- The only proof is a test: a controlled runtime test, done at a quiet time, with someone watching.
Turn this into a project
Send us the result. We will measure the real load, check the batteries and tell you whether to replace batteries, add a battery pack, or change the UPS.